A) 0
B) 1
C) 2
D) 3
E) 4
Correct Answer
verified
Multiple Choice
A) item A is the parent of item B
B) item D is on level 3
C) item A is a parent of item D
D) all of the above are true
E) none of the above is true
Correct Answer
verified
Multiple Choice
A) A
B) B
C) C
D) D
E) E
Correct Answer
verified
Multiple Choice
A) The computer can move the scheduled receipt, not the firm planned order
B) Only the scheduled receipt can occur within the planning horizon
C) Only the scheduled receipt represents a financial commitment
D) The scheduled receipt is generated from the master schedule, the firm planned order generated from MRP
Correct Answer
verified
Multiple Choice
A) Dependent demand
B) Independent demand
C) Bill of materials
D) Order quantity
Correct Answer
verified
Multiple Choice
A) dependent, dependent
B) dependent, independent
C) independent, independent
D) independent, dependent
E) none of the above answers are correct
Correct Answer
verified
Multiple Choice
A) 25
B) 30
C) 40
D) 100
E) none of the above
Correct Answer
verified
Multiple Choice
A) master scheduling
B) material requirements planning
C) capacity planning
D) production control
E) none of the above
Correct Answer
verified
Multiple Choice
A) only I is true
B) only II is true
C) only III is true
D) I and II are true
E) I, II and III are true
Correct Answer
verified
Multiple Choice
A) where-used
B) relating
C) pegging
D) any one of the above
E) none of the above
Correct Answer
verified
Multiple Choice
A) when a component changes
B) when there is a change in the use of the item
C) when the item is used in another parent
D) never
E) if the item is fully interchangeable
Correct Answer
verified
Multiple Choice
A) 0
B) 5
C) 15
D) 25
Correct Answer
verified
Multiple Choice
A) significant part numbering systems are difficult to maintain
B) it is easier to remember numbers than letters
C) a random number is an identifier not a descriptor
D) all of the above are true
Correct Answer
verified
Multiple Choice
A) a planned order for 50 should be released in period two
B) the projected available in period three is 105
C) the projected available in period three is five
D) the planned order release of 100 is in period 3
E) the planned order release of 100 is in period 5
Correct Answer
verified
Multiple Choice
A) X
B) 1
C) 2
D) 3
E) 4
Correct Answer
verified
Multiple Choice
A) Independent
B) Dependent
C) Independent and Dependent
D) None of the above
Correct Answer
verified
Multiple Choice
A) every item has more than one low-level code
B) net requirements = gross requirements + on-hand + scheduled receipts
C) each part has at least one part number, depending on where it is used
D) all of the above are true
E) none of the above is true
Correct Answer
verified
Multiple Choice
A) the current time is the beginning of the first period
B) the number of periods in the record is called the planning horizon
C) an item is considered to be available at the end of the time bucket in which it is required
D) the projected on-hand balance is for the end of the period
E) the immediate or most current period is called the action bucket
Correct Answer
verified
Multiple Choice
A) planned order releases show when the order is needed
B) when an order is released, it becomes a planned order
C) scheduled receipts show when goods were put into inventory
D) all of the above are correct
E) none of the above is correct
Correct Answer
verified
Multiple Choice
A) production activity control, purchasing, and the production plan
B) inventory status, the master production schedule, and the product structure
C) the master production schedule, inventory status, and the capacity requirements plan
D) the product structure, production activity control, and inventory status
E) the product structure, production activity control, and the master production schedule
Correct Answer
verified
Showing 1 - 20 of 41
Related Exams