In the following product trees the low level code of item D is: In the following product trees the low level code of item D is:   A)  0 B)  1 C)  2 D)  3 E)  4


A) 0
B) 1
C) 2
D) 3
E) 4

F) A) and E)
G) B) and C)

Correct Answer

verifed

verified

Which of the following statements is best? Which of the following statements is best?   A)  item A is the parent of item B B)  item D is on level 3 C)  item A is a parent of item D D)  all of the above are true E)  none of the above is true


A) item A is the parent of item B
B) item D is on level 3
C) item A is a parent of item D
D) all of the above are true
E) none of the above is true

F) None of the above
G) B) and D)

Correct Answer

verifed

verified

Given the following product tree, the parent of B is: Given the following product tree, the parent of B is:     A)  A B)  B C)  C D)  D E)  E Given the following product tree, the parent of B is:     A)  A B)  B C)  C D)  D E)  E


A) A
B) B
C) C
D) D
E) E

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified

Which of the following represents a major difference between a scheduled receipt and a firm planned order?


A) The computer can move the scheduled receipt, not the firm planned order
B) Only the scheduled receipt can occur within the planning horizon
C) Only the scheduled receipt represents a financial commitment
D) The scheduled receipt is generated from the master schedule, the firm planned order generated from MRP

E) None of the above
F) A) and C)

Correct Answer

verifed

verified

Which of the following comes directly from external customers?


A) Dependent demand
B) Independent demand
C) Bill of materials
D) Order quantity

E) A) and B)
F) B) and D)

Correct Answer

verifed

verified

B

In the product structure diagram below item A has _ demand and item D has Demand. In the product structure diagram below item A has _ demand and item D has Demand.   A)  dependent, dependent B)  dependent, independent C)  independent, independent D)  independent, dependent E)  none of the above answers are correct


A) dependent, dependent
B) dependent, independent
C) independent, independent
D) independent, dependent
E) none of the above answers are correct

F) A) and E)
G) None of the above

Correct Answer

verifed

verified

D

The following two questions use the information in this MRP record. The lead time is 3 weeks.  Week 12345 Gross requirements 6050607020 Scheduled receipts 100 Projected available 40903040 Net requirements Planned  order receipt Planned  order release 100\begin{array}{llllll}\text { Week } & 1 & 2 & 3 & 4 & 5 \\\text { Gross requirements } & 60 & 50 & 60 & 70 & 20 \\\text { Scheduled receipts } & & 100 & & &\\\text { Projected available }&40&90&30&&40\\\text { Net requirements Planned }\\\text { order receipt Planned }\\\text { order release } \quad100\end{array} -The net requirement for week four is:


A) 25
B) 30
C) 40
D) 100
E) none of the above

F) C) and E)
G) D) and E)

Correct Answer

verifed

verified

A set of priority planning techniques for planning component items below the end item level is called:


A) master scheduling
B) material requirements planning
C) capacity planning
D) production control
E) none of the above

F) None of the above
G) B) and C)

Correct Answer

verifed

verified

A multi-level bill of material: I. Reflects the way the product will be manufactured. II. Is produced by the purchasing department. III. Is a parts list only and does not contain subassemblies.


A) only I is true
B) only II is true
C) only III is true
D) I and II are true
E) I, II and III are true

F) None of the above
G) A) and B)

Correct Answer

verifed

verified

The ability to relate the demand for an item shown on an MRP record back to the particular parent causing the demand is called:


A) where-used
B) relating
C) pegging
D) any one of the above
E) none of the above

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

A bill of material for an item must change:


A) when a component changes
B) when there is a change in the use of the item
C) when the item is used in another parent
D) never
E) if the item is fully interchangeable

F) C) and E)
G) A) and E)

Correct Answer

verifed

verified

Use the following MRP record and your calculations to answer the following two questions. The component has an order quantity of 100, a safety stock of ten, and a lead time of one period. Complete the following MRP record.  Week 1234 Gross requirements 25802080 Scheduled receipts 100 Projected available 30 Net requirements  Planned order receipt  Planned order release \begin{array} { l l l l l } \text { Week } & 1 & 2 & 3 & 4 \\\text { Gross requirements } & 25 & 80 & 20 & 80 \\\text { Scheduled receipts } & 100 & & & \\\text { Projected available } &30 & & & \\\text { Net requirements } & & & \\\text { Planned order receipt } & & & \\\text { Planned order release } & & &\end{array} -The projected available in period four is:


A) 0
B) 5
C) 15
D) 25

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Which of the following statements is best regarding part numbering systems?


A) significant part numbering systems are difficult to maintain
B) it is easier to remember numbers than letters
C) a random number is an identifier not a descriptor
D) all of the above are true

E) B) and D)
F) None of the above

Correct Answer

verifed

verified

Use the following MRP record and your calculations to answer the following two questions. The component has an order quantity of 100, a safety stock of ten, and a lead time of one period. Complete the following MRP record.  Week 1234 Gross requirements 25802080 Scheduled receipts 100 Projected available 30 Net requirements  Planned order receipt  Planned order release \begin{array} { l l l l l } \text { Week } & 1 & 2 & 3 & 4 \\\text { Gross requirements } & 25 & 80 & 20 & 80 \\\text { Scheduled receipts } & 100 & & & \\\text { Projected available } &30 & & & \\\text { Net requirements } & & & \\\text { Planned order receipt } & & & \\\text { Planned order release } & & &\end{array} -Complete the above MRP record. Which of the following statements is correct?


A) a planned order for 50 should be released in period two
B) the projected available in period three is 105
C) the projected available in period three is five
D) the planned order release of 100 is in period 3
E) the planned order release of 100 is in period 5

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

In the diagram below the independent demand item is: In the diagram below the independent demand item is:   A)  X B)  1 C)  2 D)  3 E)  4


A) X
B) 1
C) 2
D) 3
E) 4

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

Service parts experience which of the following types of demand?


A) Independent
B) Dependent
C) Independent and Dependent
D) None of the above

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

Which of the following statements is best?


A) every item has more than one low-level code
B) net requirements = gross requirements + on-hand + scheduled receipts
C) each part has at least one part number, depending on where it is used
D) all of the above are true
E) none of the above is true

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

E

Which of the following is NOT true of an MRP record?


A) the current time is the beginning of the first period
B) the number of periods in the record is called the planning horizon
C) an item is considered to be available at the end of the time bucket in which it is required
D) the projected on-hand balance is for the end of the period
E) the immediate or most current period is called the action bucket

F) D) and E)
G) C) and D)

Correct Answer

verifed

verified

Which statement is correct?


A) planned order releases show when the order is needed
B) when an order is released, it becomes a planned order
C) scheduled receipts show when goods were put into inventory
D) all of the above are correct
E) none of the above is correct

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

Three inputs to the MRP process are:


A) production activity control, purchasing, and the production plan
B) inventory status, the master production schedule, and the product structure
C) the master production schedule, inventory status, and the capacity requirements plan
D) the product structure, production activity control, and inventory status
E) the product structure, production activity control, and the master production schedule

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified